Old 11-06-2008, 09:30 AM   #1
Senior Member
 
Join Date: Oct 2008
Location: Chicago, IL
Posts: 731
Default TPO job - please verify production rates

I just put together a bid for a job. Here are the details:

1 story building
165' x 175' outside measurments with a Kynar gravel stop at all 4 sides.
Current roof is a ballasted EPDM which is shrinking badly.
That is over some kind of insulation whcih I did not core but seems too to be too thin since it is over fluted metal deck.

My proposal:
Remove the gravel and dispose.
Cut back the edge of the roof to eliminate the shrinkage effect, but leave the EPDM in place. Maybe also cut back from the curbs and boxes as necessary.
Install new 45 mil TPO Mechanically attached over 1 1/2" ISO insulation. I suppose I could do EPS, but I am bidding ISO for now.
Flashing details include: 4 soil pipes 0-6" boot. 14 4x8 curbs. 12 flu pipes to be field wrapped. 10 4x4 curbs. 4 interior roof drains. 2 2x2 curbs.


When all is said and done I figure I am goign to need to order 300 squares of membrane, plus accessories, 9000 6" screws, 5000 insulation plates, 4000 seam plates and 70 pieces of kynar steel gravel stop. The price seems low at what comes up to be: $113k.

Material is going to cost me about $45k. If I use a per square price for the labor it comes up real high at 800 man hours or 20 working days

That's where I am stuck. The sale price seems ok, maybe a wee bit low. The man hours seem ridiculously high! I'm just guessing since I haven't done a TPO this big.

Comments?
__________________
-Grumpy
Chicago Gutters Chicago Roofing
Grumpy is offline   Reply With Quote
Join Roofing Talk

Join the #1 Roofing Forum Today - It's Totally Free!

RoofingTalk.com - Are you a Professional Roofing Contractor? If so we invite you to join our community and see what it has to offer. Our site is specifically designed for you and it's the leading place for roofers to meet online. No homeowners asking DIY questions. Just fellow tradesmen who enjoy talking about their business, their trade, and anything else that comes up. No matter what your specialty is you'll find that RoofingTalk.com is a great community to join. Best of all it's totally free!

Join RoofingTalk.com - Click Here JOIN FOR FREE


Warning: The topics covered on this site include activities in which there exists the potential for serious injury or death. RoofingTalk.com DOES NOT guarantee the accuracy or completeness of any information contained on this site. Always use proper safety precaution and reference reliable outside sources before attempting any construction or remodeling task!
Old 11-09-2008, 09:01 PM   #2
Member
 
Join Date: Nov 2008
Posts: 33
Default

800 hrs sounds about right if not a bit low depending on how fast your crew is and the time to remove the gravel. I'm assuming that there is pitch built in and minimal crickets to be built with taper. All the TPO I have done was either fully adhered or the 2001 system to meet uplift. A lot depends on your details and can add or subtract a ton of time, what edge detail are you using?
apehangeralfy is offline   Reply With Quote
Old 11-10-2008, 07:44 AM   #3
Senior Member
 
Join Date: Oct 2008
Location: Chicago, IL
Posts: 731
Default

Gravel stop at the edge. First wrap over the field membrane, mount the GS, then strip in the field membrane gluing it to the metal and welding it to the field, then caulk. TPO coated metal is so damned expensive.

The roof has enough slope that no puddles or ponding water was visible.
__________________
-Grumpy
Chicago Gutters Chicago Roofing
Grumpy is offline   Reply With Quote
Old 11-10-2008, 04:29 PM   #4
Member
 
Join Date: Nov 2008
Posts: 33
Default

The ones we do it gets speced to wrap the field over the edge, drip get screwed every 3", clean and prime then pressure sensitive cover strip get rolled on. The cover strip is up there to. Never had good luck with the TPO clad metal and with that many liner ft it would take forever to weld it... make sure your robot is up to snuff, I had one that acted up and my guys didn't do a test pc every day, 500 sq with intermittent welds....
apehangeralfy is offline   Reply With Quote
Old 11-10-2008, 05:30 PM   #5
Super Moderator
 
Join Date: Sep 2008
Posts: 584
Default

A style like a Hickman 2-Piece snap lock gravel stop works out pretty nicely too, if they have an approved specification alloed for it.

Ed
Ed the Roofer is offline   Reply With Quote
Old 01-06-2009, 08:57 PM   #6
Member
 
Join Date: Jan 2009
Location: NJ
Posts: 50
Default

First off I would order an extra 20 sq. of TPO....think you will be a tad short going with 300 sqs.

Secondly, don't use the glue/caulk detail for your perimeter...especially with TPO. Go with a Metal Era 2 piece edge....it will cost a little bit more but will go on quicker and save you a ton of headaches down the road.

Caulk is a maintenance item.

Peel & Stick is better than Glue/Caulk but if someone wants a heat-welded system they should get one.... no seam tape or pressure sensitive is my motto.

Then again all we do is heat welded systems so i am bias

As far as labor goes I think 600 hours is probably more accurate. Your material cost looks right. In our area (Central NJ ) that job would probably go for around $85k

Just realized this post was from November but I just joined today
SinglePlyGuy is offline   Reply With Quote
Old 01-06-2009, 10:12 PM   #7
Super Moderator
 
Join Date: Sep 2008
Posts: 584
Default

Welcome to the site SinglePlyGuy.

Why don't you make an introduction post and tell a little more about what materials you work with and for how long.

Ed
Ed the Roofer is offline   Reply With Quote
Old 01-07-2009, 12:09 PM   #8
Senior Member
 
Join Date: Oct 2008
Location: Chicago, IL
Posts: 731
Default

Wow $85k I'd lose my shirt, pants and probably my company. But then again I am told we are 1/5th where we should be in terms of production. Someone told me that job would be a 2 day job for 4 men. I laughed, although it comes from a respectable source.

FYI the customer won't even return any of my calls.
__________________
-Grumpy
Chicago Gutters Chicago Roofing
Grumpy is offline   Reply With Quote
Old 01-07-2009, 04:59 PM   #9
Member
 
Join Date: Jan 2009
Location: NJ
Posts: 50
Default

Well unfortunately thats where prices are at in NJ.

Believe me I am not really thrilled about it either. But the easy projects that you can just blow through usually dont net too well percentage-wise.

A small crew could knock that job out in 5 days max. Alot of contractors these days will take that job and bank $20k for a weeks work.
SinglePlyGuy is offline   Reply With Quote
Old 06-24-2009, 08:55 PM   #10
Member
 
Join Date: May 2009
Posts: 59
Default

Grumpy, did you get this job?
rwolfe is offline   Reply With Quote
Reply

Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are Off
Pingbacks are Off
Refbacks are Off


Top of Page | View New Posts

All times are GMT -5. The time now is 03:40 AM.


Powered by vBulletin® Version 3.7.3
Copyright ©2000 - 2010, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO 3.2.0
Roofing Talk © 2008 The Building Network LLC